Forum › Forums › General Beckenham Discussions › The Beckenham Improvements Works Updates
Be great to know if anyone is reading these and if they are helpful, please comment below
Work for week commencing the 2nd October 2017.
Phase 3 works:
· Granite paving will continue to be laid at Thorntons Corner.
· Kerbing, drainage and paving will be installed outside the Village Garage and continue west up the High Street.
· A materials compound will be located further up the High Street.
· The construction of the new planters on Beckenham Green will continue. Filling the planters will commence.
Late Working
· For the next 2-3 weeks the contractors will be working to 8pm to ensure the improvements are ready for new traffic signals to be installed.
Completed Works
· Granite paving, kerbing and parking spaces have been installed in front of the toilets and Kelsey House.
Traffic Management Issues.
*From Tuesday 29th August the High Street from the War Memorial to Thornton’s Corner will be one way. The direction of traffic will move northeast, from the War Memorial to Thornton’s Corner with diversions on Rectory Road. This one way system will be in place until the end of November 2017 when works will be suspended for the Christmas period. In January 2018 temporary one way traffic flow will be reintroduced.
Concerns have been raised regarding traffic flow at the junction with Thornton’s Corner.
TfL have investigated this issue and have adjusted them to regulate the green light timings to account for traffic flow at certain times of the day. The left turn from one section of the High Street to the other is, presently much sharper for buses, due to the works outside Kelsey Park House on the opposite corner. Buses are currently slowing to avoid safety barriers therefore forcing vehicles from Manor Road and Kelsey Park Road to wait. As the work progresses along this section of the High Street, the situation will improve.
(For reference some works such as traffic signals and power connections are conducted by outside agencies such as Transport for London and UKPN. The project does not have control of these works).
*The High Street from Thorntons Corner to Beckenham Junction has remained one directional. Consideration by the Councils Highways Department and TfL has concluded that this is the best solution during the remainder of the works. It is considered that despite diversions signs some cars would continue to drive south from Bromley Road junction and cause traffic management problems when confronted with the one directional traffic management for the High Street between Thorntons Corner and the War Memorial.
New road closures and bus diversions are in place. Helen McConnell can supply a copy of the new bus stops at the below email address.
The completed scheme
Feedback from the community has revealed that there are some incorrect preconceptions about the scheme.
• The High Street will not be pedestrianised. Improvements will however greatly improve the pedestrian environment with wider pavements, improved lighting and more and better road crossings.
• After the improvements are complete the High Street will revert to two way traffic as prior to the improvements. The larger widenings such as the North-West corner of Thorntons Corner have been designed to enable the largest road vehicles to comfortably navigate the corner in both directions. Changes to the vehicle stop lines and traffic signalling will enable vehicles to use the reduced road space with minimal impacts on traffic flows.
• No existing bus stops will be removed from the High Street. All bus stops will however be improved and will become fully disabled accessible. In order to create sufficient waiting space for passengers some bus stops will be located on what is the highway at present.
• The scheme will not introduce shared surfaces where the footway and road surface will be on the same level. Throughout the scheme a kerb will be retained between the pavement and the road and the pedestrian areas will be a traditional pavement above vehicular areas except at crossing places.
• Many of the parking spaces are inset into the paving (achieved by widening the paving not reducing it). They are flush with the pavement to avoid a trip hazard kerb.
Further information can be found at www.bromley.gov.uk/beckenhamimprovements
A Big Thank You
Increasingly the project team and FM Conway have been receiving compliments about the improvements and the site contractors. Thank you for these. It is also much appreciated that businesses are working with and acknowledging that the site contractors of FM Conway are endeavouring to minimise disruption as much as possible.
We are aware that the works do cause noise and disruption. FM Conway will try and minimise the space for materials storage outside Beckenham Green as soon as possible. In the meantime thank you for your patience if you are affected.
About the Scheme
The scheme is designed to make the town more attractive to visitors and shoppers by day and night. A major objective is to support existing businesses and encourage new businesses to invest in the town centre. The High Street investment improvements will create a more attractive and safer pedestrian environment. Improvements will include new paving and road surfacing, improved and attractive lighting, improved road crossings and bus waiting facilities, better facilities for cyclists and improved amenity spaces including Beckenham Green.
Extensive planning and consultation has been carried out since the scheme was proposed in 2012. The cooperation and input of the ‘Town Centre Team’ and its members including the Beckenham Business Association, The Beckenham Society and the Copers Cope Resident Association is gratefully acknowledged, with their input key in shaping the nature of the scheme.
Sign up for regular newsletter updates
Businesses and interested residents who want to follow the progress of the work over the 18 months duration can sign up for the regular updates that will be sent. Visit www.bromley.gov.uk/beckenhamimprovements to do this where the latest detailed traffic diversions are listed including information about bus routes and a link to TfL’s website www.tfl.gov.uk/BusChanges. .
Thank you for your understanding and support
Every effort is being made to minimise disruption and your understanding and support is appreciated in advance if there are unforeseen issues which need to be resolved. If further specific information is needed, please contact Conway’s Helen McConnell who can be contacted, for help and advice. Helen, the Liaison Officer is the scheme contact for businesses and residents. Helen can be contacted on Mobile Tel 07917 518 529 or email Beckenham@fmconway.co.uk if needed.
Dear Business Representative or Resident,
Beckenham Improvements work update
Work for week commencing the 18th September 2017.
Phase 3 works:
· In front of Kelsey house and the former toilets works will continue to excavate the highway, install additional drainage and the new introduction of new kerbing will continue. The construction of the PAD parking will also continue
· Granite paving will continue to be laid on the north-west and north-east corner of Thorntons Corner.
· Thames Water has had a problem with one of their water mains The repair works are due to be finished early in the week. The road resurfacing is due to be carried out on Friday 22nd September.
· A temporary materials compound will be located near the junction of High Street and Fairfield Road.
· The construction of the new planters on Beckenham Green will continue.
Further stakeholder consultation
Another meeting with the business community has been arranged for the 25th September 2017 at 18.45 at the Public Halls, 4 Bromley Road, BR3 5JE. The businesses likely to be affected by the Phase 3 works will be contacted directly.
Traffic Management Issues.
From Tuesday 29th August the High Street from the War Memorial to Thornton’s Corner will be one way. The direction of traffic will move northeast, from the War Memorial to Thornton’s Corner with diversions on Rectory Road. This one way system will be in place until the end of November 2017 when works will be suspended for the Christmas period. In January 2018 temporary one way traffic flow will be reintroduced.
Concerns have been raised regarding traffic flow at the junction with Thornton’s Corner. TfL have investigated this issue and have adjusted them to regulate the green light timings to account for traffic flow at certain times of the day.
The left turn from one section of the High Street to the other is, presently much sharper for buses, due to the works outside Kelsey Park House on the opposite corner. Buses are currently slowing to avoid safety barriers therefore forcing vehicles from Manor Road and Kelsey Park Road to wait. As the work progresses along this section of the High Street, the situation will improve.
(For reference some works such as traffic signals and power connections are conducted by outside agencies such as Transport for London and UKPN. The project does not have control of these works).
The High Street from Thorntons Corner to Beckenham Junction has remained one directional. Consideration by the Councils Highways Department and TfL has concluded that this is the best solution during the remainder of the works. It is considered that despite diversions signs some cars would continue to drive south from Bromley Road junction and cause traffic management problems when confronted with the one directional traffic management for the High Street between Thorntons Corner and the War Memorial.
New road closures and bus diversions are in place. Helen McConnell can supply a copy of the new bus stops at the below email address.
The completed scheme
Feedback from the community has revealed that there are some incorrect preconceptions about the scheme.
• The High Street will not be pedestrianised. Improvements will however greatly improve the pedestrian environment with wider pavements, improved lighting and more and better road crossings.
• After the improvements are complete the High Street will revert to two way traffic as prior to the improvements. The larger widenings such as the North-West corner of Thorntons Corner have been designed to enable the largest road vehicles to comfortably navigate the corner in both directions. Changes to the vehicle stop lines and traffic signalling will enable vehicles to use the reduced road space with minimal impacts on traffic flows.
• No existing bus stops will be removed from the High Street. All bus stops will however be improved and will become fully disabled accessible. In order to create sufficient waiting space for passengers some bus stops will be located on what is the highway at present.
• The scheme will not introduce shared surfaces where the footway and road surface will be on the same level. Throughout the scheme a kerb will be retained between the pavement and the road and the pedestrian areas will be a traditional pavement above vehicular areas except at crossing places.
• Many of the parking spaces are inset into the paving (achieved by widening the paving not reducing it). They are flush with the pavement to avoid a trip hazard kerb.
Further information can be found at http://www.bromley.gov.uk/beckenhamimprovements
Dear Business Representative or Resident,
Beckenham Improvements work update
Work for week commencing the 12th September 2017.
Phase 3 works:
· In front of Kelsey house and the former toilets works will continue to excavate the highway, install additional drainage and the new introduction of new kerbing will continue.
· The temporary asphalt surfacing on the north-west corner of Thornton’s Corner is being excavated for the laying of the granite paving.
· Thames Water has had a problem with one of their water mains. At present they are still investigating the problem. As a consequence surfacing work in the section of The High Street between Thornton’s Corner and Beckenham Junction has been temporarily stopped.
· The construction of the new planters on Beckenham Green will continue.
Further stakeholder consultation
Another meeting with the business community has been arranged for the 25th September 2017 at 18.45 at the Public Halls, 4 Bromley Road, BR3 5JE. The businesses likely to be affected by the Phase 3 works will be contacted directly.
Traffic Management Issues.
· From Tuesday 29th August the High Street from the War Memorial to Thornton’s Corner will be one way. The direction of traffic will move northeast, from the War Memorial to Thornton’s Corner with diversions on Rectory Road. This one way system will be in place until the end of November 2017 when works will be suspended for the Christmas period. In January 2018 temporary one way traffic flow will be reintroduced.
· Concerns have been raised regarding traffic flow at the junction with Thornton’s Corner. TfL have investigated this issue and have adjusted them to regulate the green light timings to account for traffic flow at certain times of the day. The left turn from one section of the High Street to the other is, presently much sharper for buses, due to the works outside Kelsey Park House on the opposite corner. Buses are currently slowing to avoid safety barriers therefore forcing vehicles from Manor Road and Kelsey Park Road to wait. As the work progresses along this section of the High Street, the situation will improve.
· The High Street from Thornton’s Corner to Beckenham Junction has remained one directional. Consideration by the Councils Highways Department and TfL has concluded that this is the best solution during the remainder of the works. It is considered that despite diversions signs some cars would continue to drive south from Bromley Road junction and cause traffic management problems when confronted with the one directional traffic management for the High Street between Thornton’s Corner and the War Memorial.
· (For reference some works such as traffic signals and power connections are conducted by outside agencies such as Transport for London and UKPN. The project does not have control of these works).
New road closures and bus diversions are in place. Helen McConnell can supply a copy of the new bus stops at the below email address.
The completed scheme
Feedback from the community has revealed that there are some incorrect preconceptions about the scheme.
• The asphalt at Thornton’s Corner is a temporary measure until the granite paving is laid.
• The High Street will not be pedestrianised. Improvements will however greatly improve the pedestrian environment with wider pavements, improved lighting and more and better road crossings.
• After the improvements are complete the High Street will revert to two way traffic as prior to the improvements. The larger widenings such as the North-West corner of Thorntons Corner have been designed to enable the largest road vehicles to comfortably navigate the corner in both directions. Changes to the vehicle stop lines and traffic signalling will enable vehicles to use the reduced road space with minimal impacts on traffic flows.
• No existing bus stops will be removed from the High Street. All bus stops will however be improved and will become fully disabled accessible. In order to create sufficient waiting space for passengers some bus stops will be located on what is the highway at present.
• The scheme will not introduce shared surfaces where the footway and road surface will be on the same level. Throughout the scheme a kerb will be retained and the pedestrian areas will be a traditional pavement above vehicular areas except at crossing places.
• Many of the parking spaces are inset into the paving (achieved by widening the paving not reducing it). They are flush with the pavement to avoid a trip hazard kerb.
Further information can be found at www.bromley.gov.uk/beckenhamimprovements
A Big Thank You
Increasingly the project team and FM Conway have been receiving compliments about the improvements and the site contractors. Thank you for these. It is also much appreciated that businesses are working with and acknowledging that the site contractors of FM Conway are endeavouring to minimise disruption as much as possible.
We are aware that the works do cause noise and disruption. FM Conway will try and minimise the space for materials storage outside Beckenham Green as soon as possible. In the meantime thank you for your patience if you are affected.
About the Scheme
The scheme is designed to make the town more attractive to visitors and shoppers by day and night. A major objective is to support existing businesses and encourage new businesses to invest in the town centre. The High Street investment improvements will create a more attractive and safer pedestrian environment. Improvements will include new paving and road surfacing, improved and attractive lighting, improved road crossings and bus waiting facilities, better facilities for cyclists and improved amenity spaces including Beckenham Green.
Extensive planning and consultation has been carried out since the scheme was proposed in 2012. The cooperation and input of the ‘Town Centre Team’ and its members including the Beckenham Business Association, The Beckenham Society and the Copers Cope Resident Association is gratefully acknowledged, with their input key in shaping the nature of the scheme.
Sign up for regular newsletter updates
Businesses and interested residents who want to follow the progress of the work over the 18 months duration can sign up for the regular updates that will be sent. Visit www.bromley.gov.uk/beckenhamimprovements to do this where the latest detailed traffic diversions are listed including information about bus routes and a link to TfL’s website www.tfl.gov.uk/BusChanges. .
Thank you for your understanding and support
Every effort is being made to minimise disruption and your understanding and support is appreciated in advance if there are unforeseen issues which need to be resolved. If further specific information is needed, please contact Conway’s Helen McConnell who can be contacted, for help and advice. Helen, the Liaison Officer is the scheme contact for businesses and residents. Helen can be contacted on Mobile Tel 07917 518 529 or email Beckenham@fmconway.co.uk if needed.
Follow us on Twitter @FMConwayltd or find out more about our unique self-delivery model through our corporate animation on FM Conway Youtube Please note, we do not accept service of any legal process by fax or electronic means. Legal process should be served formally unless otherwise agreed in writing by a statutory director. F M Conway Limited is a company registered in England and Wales with company number 706445 VAT number is 205429289 Think before you print – Reduce Re-use Recycle Disclaimer : – The information contained in this e-mail is intended only for the individual or entity to whom it is addressed. Its contents (including any attachments) are confidential and may contain privileged information. If you are not an intended recipient you must not use, disclose, disseminate, copy or print its contents. If you receive this email in error, please delete and destroy the message and notify the sender by reply email. All messages passing through this gateway are checked for viruses but we strongly recommend that you check for viruses using your own virus scanner as F M Conway Ltd will not take responsibility for any damage caused as a result of virus infection.
Friday 18th August 2017
Beckenham Improvements work update
Work for week commencing the 21st August 2017
· Surfacing work between Manor Road and Albermarle Road will be done between 8pm-5am starting Monday 21st until Saturday 26th at 5:00am. The full length of this section of the High Street will be closed between these dates at 8:00pm-5:00am, with diversions in place.
· Letters to residents and businesses directly impacted by this section of work have already been notified. All residents in Rokewood Apartments, St Brides House or The Mews, who have not received a letter detailing the night surfacing work should contact Conway’s Liaison Office, Helen McConnell on tel 07917 518 529 or email Beckenham@fmconway.co.uk
· Work will continue in front of Gallery 17 until early next week.
· The construction of the new planters on Beckenham Green will continue.
· The footpath adjacent to Beckenham Green is anticipated to reopen early next week.
For reference some works such as traffic signals and power connections are conducted by outside agencies such as Transport for London and UKPN. The project does not have control of these works.
Previous completed works
· Temporary asphalt surface has been laid on the corner of Albemarle Road and the High Street.
· Work on Church Ave junction has been completed regarding slight adjustments to the existing improvements.
The completed scheme
Feedback from the community has revealed that there are some incorrect preconceptions about the scheme.
• The asphalt at Thornton’s Corner is a temporary measure until the granite paving is laid.
• The High Street will not be pedestrianised. Improvements will however greatly improve the pedestrian environment with wider pavements, improved lighting and more
and better road crossings.
• After the improvements are complete the High Street will revert to two way traffic as prior to the improvements. The larger widenings such as the North-West corner of Thorntons Corner have been designed to enable the largest road vehicles to comfortably navigate the corner in both directions. Changes to the vehicle stop lines and traffic signalling will enable vehicles to use the reduced road space with minimal impacts on traffic flows.
• No existing bus stops will be removed from the High Street. All bus stops will however be improved and will become fully disabled accessible. In order to create sufficient waiting space for passengers some bus stops will be located on what is the highway at present.
• The scheme will not introduce shared surfaces where the footway and road surface will be on the same level. Throughout the scheme a kerb will be retained and the pedestrian areas will be a traditional pavement above vehicular areas except at crossing places.
• Many of the parking spaces are inset into the paving (achieved by widening the paving not reducing it). They are flush with the pavement to avoid a trip hazard kerb.
Further information can be found at http://www.bromley.gov.uk/beckenhamimprovements
A Big Thank You
Increasingly the project team and FM Conway have been receiving compliments about the improvements and the site contractors. Thank you for these. It is also much appreciated that businesses are working with and acknowledging that the site contractors of FM Conway are endeavouring to minimise disruption as much as possible.
We are aware that the works do cause noise and disruption. FM Conway will try and minimise the space for materials storage outside Beckenham Green as soon as possible. In the meantime thank you for your patience if you are affected.
About the scheme
The scheme is designed to make the town more attractive to visitors and shoppers by day and night. A major objective is to support existing businesses and encourage new businesses to invest in the town centre. The High Street investment improvements will create a more attractive and safer pedestrian environment. Improvements will include new paving and road surfacing, improved and attractive lighting, improved road crossings and bus waiting facilities, better facilities for cyclists and improved amenity spaces including Beckenham Green.
Extensive planning and consultation has been carried out since the scheme was proposed in 2012. The cooperation and input of the ‘Town Centre Team’ and its members including the Beckenham Business Association, The Beckenham Society and the Copers Cope Resident Association is gratefully acknowledged, with their input key in shaping the nature of the scheme.
Sign up for regular newsletter updates
Businesses and interested residents who want to follow the progress of the work over the 18 months duration can sign up for the regular updates that will be sent. Visit http://www.bromley.gov.uk/beckenhamimprovements to do this where the latest detailed traffic diversions are listed including information about bus routes and a link to TfL’s website http://www.tfl.gov.uk/BusChanges. .
Thank you for your understanding and support
Every effort is being made to minimise disruption and your understanding and support is appreciated in advance if there are unforeseen issues which need to be resolved. If further specific information is needed, please contact Conway’s Helen McConnell who can be contacted, for help and advice. Helen, the Liaison Officer is the scheme contact for businesses and residents. Helen can be contacted on Mobile Tel 07917 518 529 or email Beckenham@fmconway.co.uk if needed.
Friday 11th August 2017
Dear Business Representative or Resident,
Beckenham Improvements work update
Work for week commencing the 14th August 2017.
· Drainage work and kerbing will continue between St Brides House and Gallery 17. Works in front of shop entrances will be completed out of hours for those retailers affected.
· Asphalt will be laid as a temporary surface on the corner of Albemarle Road and the High Street. It is anticipated this footpath will open towards the end of week commencing 14th August.
· At Church Ave junction slight adjustments will be made to the existing improvements.
· Roadside compounds along the High Street outside NatWest and St George’s Church will be cleared in preparation for resurfacing work to take place week commencing 21st August. Further details about the resurfacing will be included in next week’s update, but all residents and retailers along this section of the High Street will be informed next week.
· The construction of the new planters on Beckenham Green will continue.
For reference some works such as traffic signals and power connections are conducted by outside agencies such as Transport for London and UKPN. The project does not have control of these works.
Previous completed works
· Paving and kerbing completed beyond the entrance to St Brides House.
· Block paving adjoining the planters on Beckenham Green has been completed.
· Transport for London traffic signals work at the Bromley Road/Church Ave/High Street Junction.
The completed scheme
Feedback from the community has revealed that there are some incorrect preconceptions about the scheme.
• The asphalt at Thornton’s Corner is a temporary measure until the granite
paving is laid.
• The High Street will not be pedestrianised. Improvements will however greatly improve the pedestrian environment with wider pavements, improved lighting and more and better road crossings.
• After the improvements are complete the High Street will revert to two way traffic as prior to the improvements. The larger widenings such as the North-West corner of Thorntons Corner have been designed to enable the largest road vehicles to comfortably navigate the corner in both directions. Changes to the vehicle stop lines and traffic signalling will enable vehicles to use the reduced road space with minimal impacts on traffic flows.
• No existing bus stops will be removed from the High Street. All bus stops will however be improved and will become fully disabled accessible. In order to create sufficient waiting space for passengers some bus stops will be located on what is the highway at present.
• The scheme will not introduce shared surfaces where the footway and road surface will be on the same level. Throughout the scheme a kerb will be retained and the pedestrian areas will be a traditional pavement above vehicular areas except at crossing places.
• Many of the parking spaces are inset into the paving (achieved by widening the paving not reducing it). They are flush with the pavement to avoid a trip hazard kerb.
Further information can be found at http://www.bromley.gov.uk/beckenhamimprovements
A Big Thank You
Increasingly the project team and FM Conway have been receiving compliments about the improvements and the site contractors. Thank you for these. It is also much appreciated that businesses are working with and acknowledging that the site contractors of FM Conway are endeavouring to minimise disruption as much as possible.
We are aware that the works do cause noise and disruption. FM Conway will try and minimise the space for materials storage outside Beckenham Green as soon as possible. In the meantime thank you for your patience if you are affected.
About the scheme
The scheme is designed to make the town more attractive to visitors and shoppers by day and night. A major objective is to support existing businesses and encourage new businesses to invest in the town centre. The High Street investment improvements will create a more attractive and safer pedestrian environment. Improvements will include new paving and road surfacing, improved and attractive lighting, improved road crossings and bus waiting facilities, better facilities for cyclists and improved amenity spaces including Beckenham Green.
Extensive planning and consultation has been carried out since the scheme was proposed in 2012. The cooperation and input of the ‘Town Centre Team’ and its members including the Beckenham Business Association, The Beckenham Society and the Copers Cope Resident Association is gratefully acknowledged, with their input key in shaping the nature of the scheme.
Sign up for regular newsletter updates
Businesses and interested residents who want to follow the progress of the work over the 18 months duration can sign up for the regular updates that will be sent. Visit http://www.bromley.gov.uk/beckenhamimprovements to do this where the latest detailed traffic diversions are listed including information about bus routes and a link to TfL’s website http://www.tfl.gov.uk/BusChanges. .
Thank you for your understanding and support
Every effort is being made to minimise disruption and your understanding and support is appreciated in advance if there are unforeseen issues which need to be resolved. If further specific information is needed, please contact Conway’s Helen McConnell who can be contacted, for help and advice. Helen, the Liaison Officer is the scheme contact for businesses and residents. Helen can be contacted on Mobile Tel 07917 518 529 or email Beckenham@fmconway.co.uk if needed.
Friday 28th July 2017
Beckenham Improvements work update
Work for weeks commencing the 7th August 2017.
· Kerb laying, drainage work and paving between Beckenham Supermarket and Gallery 17.
· The entrance to St Brides House will be relaid on the weekend of the 5th & 6th of August. All residents and retailers using this entrance are aware that this work will be taking place this weekend. All residents parking will be re located whilst this work is carried out. It is hoped that by Monday morning this entrance will be opened, however additional days may be required to complete this work.
· The construction of the new planters on Beckenham Green will continue.
· Transport for London traffic signals work at the Bromley Road/Church Road/High Street Junction.
· Pavement laying will continue adjoining the planters on Beckenham Green and will be completed by the 11th August.
For reference some works such as traffic signals and power connections are conducted by outside agencies such as Transport for London and UKPN. The project does not have control of these works and therefore trenches such as at the Albemarle and High Street junction cannot be filled.
Previous completed works
· Paving and kerbing completed to Marks and Spencer. Paving commenced outside of Beckenham Green.
The completed scheme
Feedback from the community has revealed that there are some incorrect preconceptions about the scheme.
• The asphalt at Thornton’s Corner is a temporary measure until the granite paving is laid.
• The High Street will not be pedestrianised. Improvements will however greatly improve the pedestrian environment with wider pavements, improved lighting and more and better road crossings.
• After the improvements are complete the High Street will revert to two way traffic as prior to the improvements. The larger widenings such as the North-West corner of Thorntons Corner have been designed to enable the largest road vehicles to comfortably navigate the corner in both directions. Changes to the vehicle stop lines and traffic signalling will enable vehicles to use the reduced road space with minimal impacts on traffic flows.
• No existing bus stops will be removed from the High Street. All bus stops will however be improved and will become fully disabled accessible. In order to create sufficient waiting space for passengers some bus stops will be located on what is the highway at present.
• The scheme will not introduce shared surfaces where the footway and road surface will be on the same level. Throughout the scheme a kerb will be retained and the pedestrian areas will be a traditional pavement above vehicular areas except at crossing places.
Further information can be found at http://www.bromley.gov.uk/beckenhamimprovements
A Big Thank You
Increasingly the project team and FM Conway have been receiving compliments about the improvements and the site contractors. Thank you for these. It is also much appreciated that businesses are working with and acknowledging that the site contractors of FM Conway are endeavouring to minimise disruption as much as possible.
We are aware that the works do cause noise and disruption. FM Conway will try and minimise the space for materials storage outside Beckenham Green as soon as possible. In the meantime thank you for your patience if you are affected.
About the scheme
The scheme is designed to make the town more attractive to visitors and shoppers by day and night. A major objective is to support existing businesses and encourage new businesses to invest in the town centre. The High Street investment improvements will create a more attractive and safer pedestrian environment. Improvements will include new paving and road surfacing, improved and attractive lighting, improved road crossings and bus waiting facilities, better facilities for cyclists and improved amenity spaces including Beckenham Green.
Extensive planning and consultation has been carried out since the scheme was proposed in 2012. The cooperation and input of the ‘Town Centre Team’ and its members including the Beckenham Business Association, The Beckenham Society and the Copers Cope Resident Association is gratefully acknowledged, with their input key in shaping the nature of the scheme.
Sign up for regular newsletter updates
Businesses and interested residents who want to follow the progress of the work over the 18 months duration can sign up for the regular updates that will be sent. Visit http://www.bromley.gov.uk/beckenhamimprovements to do this where the latest detailed traffic diversions are listed including information about bus routes and a link to TfL’s website http://www.tfl.gov.uk/BusChanges. .
Thank you for your understanding and support
Every effort is being made to minimise disruption and your understanding and support is appreciated in advance if there are unforeseen issues which need to be resolved. If further specific information is needed, please contact Conway’s Helen McConnell who can be contacted, for help and advice. Helen, the Liaison Officer is the scheme contact for businesses and residents. Helen can be contacted on Mobile Tel 07917 518 529 or email Beckenham@fmconway.co.uk if needed.
Dear Business Representative or Resident,
Friday 28th July 2017
Beckenham Improvements work update
Work for weeks commencing the 30th July 2017.
· Kerb laying, drainage work and paving continuing north from Church Avenue.
· The construction of the new planters on Beckenham Green will continue.
· Transport for London traffic signals work at the Bromley Road/Church Road/High Street Junction to be completed by the end of the week.
· Pavement laying will continue adjoining the planters on Beckenham Green and will be completed by the 11th August.
For reference some works such as traffic signals and power connections are conducted by outside agencies such as Transport for London and UKPN. The project does not have control of these works and therefore trenches such as at the Albemarle and High Street junction cannot be filled.
Previous completed works
· Paving and kerbing completed to Marks and Spencer.
The completed scheme
Feedback from the community has revealed that there are some incorrect preconceptions about the scheme.
• The asphalt at Thornton’s Corner is a temporary measure until the granite paving is laid.
• The High Street will not be pedestrianised. Improvements will however greatly improve the pedestrian environment with wider pavements, improved lighting and more and better road crossings.
• After the improvements are complete the High Street will revert to two way traffic as prior to the improvements. The larger widenings such as the North-West corner of Thorntons Corner have been designed to enable the largest road vehicles to comfortably navigate the corner in both directions. Changes to the vehicle stop lines and traffic signalling will enable vehicles to use the reduced road space with minimal impacts on traffic flows.
• No existing bus stops will be removed from the High Street. All bus stops will however be improved and will become fully disabled accessible. In order to create sufficient waiting space for passengers some bus stops will be located on what is the highway at present.
• The scheme will not introduce shared surfaces where the footway and road surface will be on the same level. Throughout the scheme a kerb will be retained and the pedestrian areas will be a traditional pavement above vehicular areas except at crossing places.
Further information can be found at http://www.bromley.gov.uk/beckenhamimprovements
A Big Thank You
Increasingly the project team and FM Conway have been receiving compliments about the improvements and the site contractors. Thank you for these. It is also much appreciated that businesses are working with and acknowledging that the site contractors of FM Conway are endeavouring to minimise disruption as much as possible.
We are aware that the works do cause noise and disruption. FM Conway will try and minimise the space for materials storage outside Beckenham Green as soon as possible. In the meantime thank you for your patience if you are affected.
About the scheme
The scheme is designed to make the town more attractive to visitors and shoppers by day and night. A major objective is to support existing businesses and encourage new businesses to invest in the town centre. The High Street investment improvements will create a more attractive and safer pedestrian environment. Improvements will include new paving and road surfacing, improved and attractive lighting, improved road crossings and bus waiting facilities, better facilities for cyclists and improved amenity spaces including Beckenham Green.
Extensive planning and consultation has been carried out since the scheme was proposed in 2012. The cooperation and input of the ‘Town Centre Team’ and its members including the Beckenham Business Association, The Beckenham Society and the Copers Cope Resident Association is gratefully acknowledged, with their input key in shaping the nature of the scheme.
Sign up for regular newsletter updates
Businesses and interested residents who want to follow the progress of the work over the 18 months duration can sign up for the regular updates that will be sent. Visit http://www.bromley.gov.uk/beckenhamimprovements to do this where the latest detailed traffic diversions are listed including information about bus routes and a link to TfL’s website http://www.tfl.gov.uk/BusChanges.
Thank you for your understanding and support.
Every effort is being made to minimise disruption and your understanding and support is appreciated in advance if there are unforeseen issues which need to be resolved. If further specific information is needed, please contact Conway’s Helen McConnell who can be contacted, for help and advice. Helen, the Liaison Officer is the scheme contact for businesses and residents. Helen can be contacted on Mobile Tel 07917 518 529 or email Beckenham@fmconway.co.uk if needed.
Dear Business Representative or Resident,
Friday 28th July 2017
Beckenham Improvements work update
Work for weeks commencing the 30th July 2017.
· Kerb laying, drainage work and paving continuing north from Church Avenue.
· The construction of the new planters on Beckenham Green will continue.
· Transport for London traffic signals work at the Bromley Road/Church Road/High Street Junction to be completed by the end of the week.
· Pavement laying will continue adjoining the planters on Beckenham Green and will be completed by the 11th August.
For reference some works such as traffic signals and power connections are conducted by outside agencies such as Transport for London and UKPN. The project does not have control of these works and therefore trenches such as at the Albemarle and High Street junction cannot be filled.
Previous completed works
· Paving and kerbing completed to Marks and Spencer.
The completed scheme
Feedback from the community has revealed that there are some incorrect preconceptions about the scheme.
• The asphalt at Thornton’s Corner is a temporary measure until the granite paving is laid.
• The High Street will not be pedestrianised. Improvements will however greatly improve the pedestrian environment with wider pavements, improved lighting and more and better road crossings.
• After the improvements are complete the High Street will revert to two way traffic as prior to the improvements. The larger widenings such as the North-West corner of Thorntons Corner have been designed to enable the largest road vehicles to comfortably navigate the corner in both directions. Changes to the vehicle stop lines and traffic signalling will enable vehicles to use the reduced road space with minimal impacts on traffic flows.
• No existing bus stops will be removed from the High Street. All bus stops will however be improved and will become fully disabled accessible. In order to create sufficient waiting space for passengers some bus stops will be located on what is the highway at present.
• The scheme will not introduce shared surfaces where the footway and road surface will be on the same level. Throughout the scheme a kerb will be retained and the pedestrian areas will be a traditional pavement above vehicular areas except at crossing places.
Further information can be found at http://www.bromley.gov.uk/beckenhamimprovements
A Big Thank You
Increasingly the project team and FM Conway have been receiving compliments about the improvements and the site contractors. Thank you for these. It is also much appreciated that businesses are working with and acknowledging that the site contractors of FM Conway are endeavouring to minimise disruption as much as possible.
We are aware that the works do cause noise and disruption. FM Conway will try and minimise the space for materials storage outside Beckenham Green as soon as possible. In the meantime thank you for your patience if you are affected.
About the scheme
The scheme is designed to make the town more attractive to visitors and shoppers by day and night. A major objective is to support existing businesses and encourage new businesses to invest in the town centre. The High Street investment improvements will create a more attractive and safer pedestrian environment. Improvements will include new paving and road surfacing, improved and attractive lighting, improved road crossings and bus waiting facilities, better facilities for cyclists and improved amenity spaces including Beckenham Green.
Extensive planning and consultation has been carried out since the scheme was proposed in 2012. The cooperation and input of the ‘Town Centre Team’ and its members including the Beckenham Business Association, The Beckenham Society and the Copers Cope Resident Association is gratefully acknowledged, with their input key in shaping the nature of the scheme.
Sign up for regular newsletter updates
Businesses and interested residents who want to follow the progress of the work over the 18 months duration can sign up for the regular updates that will be sent. Visit http://www.bromley.gov.uk/beckenhamimprovements to do this where the latest detailed traffic diversions are listed including information about bus routes and a link to TfL’s website http://www.tfl.gov.uk/BusChanges.
Thank you for your understanding and support.
Every effort is being made to minimise disruption and your understanding and support is appreciated in advance if there are unforeseen issues which need to be resolved. If further specific information is needed, please contact Conway’s Helen McConnell who can be contacted, for help and advice. Helen, the Liaison Officer is the scheme contact for businesses and residents. Helen can be contacted on Mobile Tel 07917 518 529 or email Beckenham@fmconway.co.uk if needed.
Dear Business Representative or Resident,
Friday 21st July 2017
Beckenham Improvements work update
Work for weeks commencing the 24th July 2017.
· Kerb laying and paving continuing north from Church Avenue.
· The construction of the new planters on Beckenham Green will continue.
· Transport for London traffic signals work at the Bromley Road/Church Road/High Street Junction are continuing. The old traffic islands at this junction will be removed.
· Pavement laying will commence adjoining the planters on Beckenham Green.
In order to ensure the completion of Phase 2 on programme Conway’s will be working extended hours to 8pm and at the weekend.
For reference some works such as traffic signals and power connections are conducted by outside agencies such as Transport for London and UKPN. The project does not have control of these works and therefore trenches such as at the Albemarle and High Street junction cannot be filled.
Previous completed works
· At the corner of Church Avenue and High Street; kerb, drainage, paving have been completed.
The completed scheme
Feedback from the community has revealed that there are some incorrect preconceptions about the scheme.
• The asphalt at Thornton’s Corner is a temporary measure until the granite paving is laid.
• The High Street will not be pedestrianised. Improvements will however greatly improve the pedestrian environment with wider pavements, improved lighting and more and better road crossings.
• After the improvements are complete the High Street will revert to two way traffic as prior to the improvements. The larger widenings such as the North-West corner of Thorntons Corner have been designed to enable the largest road vehicles to comfortably navigate the corner in both directions. Changes to the vehicle stop lines and traffic signalling will enable vehicles to use the reduced road space with minimal impacts on traffic flows.
• No existing bus stops will be removed from the High Street. All bus stops will however be improved and will become fully disabled accessible. In order to create sufficient waiting space for passengers some bus stops will be located on what is the highway at present.
• The scheme will not introduce shared surfaces where the footway and road surface will be on the same level. Throughout the scheme a kerb will be retained and the pedestrian areas will be a traditional pavement above vehicular areas except at crossing places.
Further information can be found at http://www.bromley.gov.uk/beckenhamimprovements
A Big Thank You
Increasingly the project team and FM Conway have been receiving compliments about the improvements and the site contractors. Thank you for these. It is also much appreciated that businesses are working with and acknowledging that the site contractors of FM Conway are endeavouring to minimise disruption as much as possible.
We are aware that the works do cause noise and disruption. FM Conway will try and minimise the space for materials storage outside Beckenham Green as soon as possible. In the meantime thank you for your patience if you are affected.
About the scheme
The scheme is designed to make the town more attractive to visitors and shoppers by day and night. A major objective is to support existing businesses and encourage new businesses to invest in the town centre. The High Street investment improvements will create a more attractive and safer pedestrian environment. Improvements will include new paving and road surfacing, improved and attractive lighting, improved road
crossings and bus waiting facilities, better facilities for cyclists and improved amenity spaces including Beckenham Green.
Extensive planning and consultation has been carried out since the scheme was proposed in 2012. The cooperation and input of the ‘Town Centre Team’ and its members including the Beckenham Business Association, The Beckenham Society and the Copers Cope Resident Association is gratefully acknowledged, with their input key in shaping the nature of the scheme.
Sign up for regular newsletter updates
Businesses and interested residents who want to follow the progress of the work over the 18 months duration can sign up for the regular updates that will be sent. Visit http://www.bromley.gov.uk/beckenhamimprovements to do this where the latest detailed traffic diversions are listed including information about bus routes and a link to TfL’s website http://www.tfl.gov.uk/BusChanges.
.
Thank you for your understanding and support
Every effort is being made to minimise disruption and your understanding and support is appreciated in advance if there are unforeseen issues which need to be resolved. If further specific information is needed, please contact Conway’s Helen McConnell who can be contacted, for help and advice. Helen, the Liaison Officer is the scheme contact for businesses and residents. Helen can be contacted on Mobile Tel 07917 518 529 or email Beckenham@fmconway.co.uk if needed.
Dear Business Representative or Resident,
Beckenham Improvements work update
Work for weeks commencing the 17th July 2017.
· At the corner of Church Avenue and High Street; kerb, drainage and traffic signals work will continue.
· Kerb laying and paving continuing north from Church Avenue.
· The construction of the new planters on Beckenham Green will continue.
In order to ensure the completion of Phase 2 on programme Conway’s will be working extended hours to 8pm and at the weekend.
For reference, in the week commencing the 24th July 2017 the paving adjacent the planters is anticipated to commence.
Previous completed works
· Footway excavation and sett laying between Belmont Dry Cleaners and The Dance Studio.
· Construction of the parking bays between The Dance Studio and Lloyds Bank.
The completed scheme
Feedback from the community has revealed that there are some incorrect preconceptions about the scheme :-
• The asphalt at Thornton’s Corner is a temporary measure until the granite paving is laid.
• The High Street will not be pedestrianised. Improvements will however greatly improve the pedestrian environment with wider pavements, improved lighting and more and better road crossings.
• After the improvements are complete the High Street will revert to two way traffic as prior to the improvements. The larger widenings such as the North-West corner of Thornton’s Corner have been designed to enable the largest road vehicles to comfortably navigate the corner in both directions. Changes to the vehicle stop lines and traffic signalling will enable vehicles to use the reduced road space with minimal impacts on traffic flows.
• No existing bus stops will be removed from the High Street. All bus stops will however be improved and will become fully disabled accessible. In order to create sufficient waiting space for passengers some bus stops will be located on what is the highway at present.
• The scheme will not introduce shared surfaces where the footway and road surface will be on the same level. Throughout the scheme a kerb will be retained and the pedestrian areas will be a traditional pavement above vehicular areas except at crossing places.
Further information can be found at www.bromley.gov.uk/beckenhamimprovements
A Big Thank You
Increasingly the project team and FM Conway have been receiving compliments about the improvements and the site contractors. Thank you for these. It is also much appreciated that businesses are working with and acknowledging that the site contractors of FM Conway are endeavouring to minimise disruption as much as possible.
We are aware that the works do cause noise and disruption. FM Conway will try and minimise the space for materials storage outside Beckenham Green as soon as possible. In the meantime thank you for your patience if you are affected.
About the scheme
The scheme is designed to make the town more attractive to visitors and shoppers by day and night. A major objective is to support existing businesses and encourage new businesses to invest in the town centre. The High Street investment improvements will create a more attractive and safer pedestrian environment. Improvements will include new paving and road surfacing, improved and attractive lighting, improved road crossings and bus waiting facilities, better facilities for cyclists and improved amenity spaces including Beckenham Green.
Extensive planning and consultation has been carried out since the scheme was proposed in 2012. The cooperation and input of the ‘Town Centre Team’ and its members including the Beckenham Business Association, The Beckenham Society and the Copers Cope Resident Association is gratefully acknowledged, with their input key in shaping the nature of the scheme.
Sign up for regular newsletter updates
Businesses and interested residents who want to follow the progress of the work over the 18 months duration can sign up for the regular updates that will be sent. Visitwww.bromley.gov.uk/beckenhamimprovements to do this where the latest detailed traffic diversions are listed including information about bus routes and a link to TfL’s website www.tfl.gov.uk/BusChanges.
.Thank you for your understanding and support
Every effort is being made to minimise disruption and your understanding and support is appreciated in advance if there are unforeseen issues which need to be resolved. If further specific information is needed, please contact Conway’s Helen McConnell who can be contacted, for help and advice. Helen, the Liaison Officer is the scheme contact for businesses and residents.
Helen can be contacted on Mobile Tel 07917 518 529 or email Beckenham@fmconway.co.uk if needed.
Dear Business Representative or Resident,
Friday 30th June 2017
Beckenham Improvements work update
Work for weeks commencing the 3rd July 2017.
· Kerb laying and new paving will commence north from The Big Breakfast towards Church Avenue. Car parking will be suspended at this location.
· Installation of granite sett paving in the parking bays at Thornton’s Corner.
· The paving adjoining Jumping Beans will be completed now that the scaffolding in situ has been removed.
· The construction of the new planters on Beckenham Green will continue.
Previous completed works
· Thornton’s corner buildout has been surfaced in temporary surfacing and opened to pedestrians.
· Strengthening materials in the loading bays at Thornton’s corner have been laid
· Kerb laying and new paving has been completed outside Pierluigis.
About the scheme
The scheme is designed to make the town more attractive to visitors and shoppers by day and night. A major objective is to support existing businesses and encourage new businesses to invest in the town centre. The High Street investment improvements will create a more attractive and safer pedestrian environment. Improvements will include new paving and road surfacing, improved and attractive lighting, improved road crossings and bus waiting facilities, better facilities for cyclists and improved amenity spaces including Beckenham Green.
Extensive planning and consultation has been carried out since the scheme was proposed in 2012. The cooperation and input of the ‘Town Centre Team’ and its members including the Beckenham Business Association, The Beckenham Society and
the Copers Cope Resident Association is gratefully acknowledged, with their input key in shaping the nature of the scheme.
Sign up for regular newsletter updates
Businesses and interested residents who want to follow the progress of the work over the next 18 months can sign up for the regular updates that will be sent. Visit http://www.bromley.gov.uk/beckenhamimprovements to do this where the latest detailed traffic diversions are listed including information about bus routes and a link to TfL’s website http://www.tfl.gov.uk/BusChanges.
.
Thank you for your understanding and support
Every effort is being made to minimise disruption and your understanding and support is appreciated in advance if there are unforeseen issues which need to be resolved. If further specific information is needed, please contact Conway’s Helen McConnell who can be contacted, for help and advice. Helen, the Liaison Officer is the scheme contact for businesses and residents. Helen can be contacted on Mobile Tel 07917 518 529 or email Beckenham@fmconway.co.uk if needed.
Dear Business Representative or Resident,
Friday 30th June 2017
Beckenham Improvements work update
Work for weeks commencing the 3rd July 2017.
· Kerb laying and new paving will commence north from The Big Breakfast towards Church Avenue. Car parking will be suspended at this location.
· Installation of granite sett paving in the parking bays at Thornton’s Corner.
· The paving adjoining Jumping Beans will be completed now that the scaffolding in situ has been removed.
· The construction of the new planters on Beckenham Green will continue.
Previous completed works
· Thornton’s corner buildout has been surfaced in temporary surfacing and opened to pedestrians.
· Strengthening materials in the loading bays at Thornton’s corner have been laid
· Kerb laying and new paving has been completed outside Pierluigis.
About the scheme
The scheme is designed to make the town more attractive to visitors and shoppers by day and night. A major objective is to support existing businesses and encourage new businesses to invest in the town centre. The High Street investment improvements will create a more attractive and safer pedestrian environment. Improvements will include new paving and road surfacing, improved and attractive lighting, improved road crossings and bus waiting facilities, better facilities for cyclists and improved amenity spaces including Beckenham Green.
Extensive planning and consultation has been carried out since the scheme was proposed in 2012. The cooperation and input of the ‘Town Centre Team’ and its members including the Beckenham Business Association, The Beckenham Society and
the Copers Cope Resident Association is gratefully acknowledged, with their input key in shaping the nature of the scheme.
Sign up for regular newsletter updates
Businesses and interested residents who want to follow the progress of the work over the next 18 months can sign up for the regular updates that will be sent. Visit http://www.bromley.gov.uk/beckenhamimprovements to do this where the latest detailed traffic diversions are listed including information about bus routes and a link to TfL’s website http://www.tfl.gov.uk/BusChanges.
.
Thank you for your understanding and support
Every effort is being made to minimise disruption and your understanding and support is appreciated in advance if there are unforeseen issues which need to be resolved. If further specific information is needed, please contact Conway’s Helen McConnell who can be contacted, for help and advice. Helen, the Liaison Officer is the scheme contact for businesses and residents. Helen can be contacted on Mobile Tel 07917 518 529 or email Beckenham@fmconway.co.uk if needed.
Improvement Works update courtesy of F M Conway contractor for the works.
Work for weeks commencing the 26th June 2017.
Kerb laying and new paving will commence north from Pierluigis towards Church Avenue. Car parking will be suspended at this location.
Strengthening materials will continue to be laid under the new parking bays along The High Street between Rokewood Apartments and Thornton’s Corner.
Additional drainage will continue to be installed at Thorntons Corner and new kerbing will be completed.
Temporary surfacing will be laid at Thorntons Corner to reopen the pavement and remove the safety barriers.
The construction of the new planters on Beckenham Green will continue.
Previous completed works
Structural works for the Beckenham Green planters has continued.
The crossover to Rokeswood Apartments was completed (1 day earlier than anticipated).
Drainage, road strengthening and kerbing has been laid at Thorntons Corner.
Dear Business Representative or Resident,
Friday 16th June 2017
Beckenham Improvements work update
Work for weeks commencing the 19th June 2017.
· New paving will be laid in the crossover to Rokeswood Apartments.
The entrance to Rokewood Apartments will be closed to vehicles for a minimum time from 8:00am on Tuesday 20th June through to Thursday 22nd at 16:30pm. Residents and users of this car park have being notified. Alternative parking will be arranged during this time for authorised users. If you do not need to use your car during these dates it can remain in situ.
If you are affected by this and have not contacted FM Conway’s liaison officer Helen McConnell please could you email Beckenham@fmconway.co.uk detailing your address, car make, model and registration number. Alternatively you can call Helen on 07917 518 529
· Strengthening materials will be laid under the new parking bays along The High Street between Rokewood Apartments and Thornton’s Corner.
· Additional drainage will be installed between 94 and 106 High Street. New kerbing will be completed.
· The construction of the new planters on Beckenham Green will continue. The structures have been designed in consultation with the Councils arboriculturalist. Each root will be boxed in a pipe/chamber to protect it with leverage for growth.
· Transport for London will continue to carry out modification works to the traffic signals on the corner of Albemarle Road and the High Street.
Previous completed works
· New kerbs have been laid between the Rokewood Apartments to Thornton’s Corner.
· Structural works for the Beckenham Green planters has continued.
About the scheme
The scheme is designed to make the town more attractive to visitors and shoppers by day and night. A major objective is to support existing businesses and encourage new businesses to invest in the town centre. The High Street investment improvements will create a more attractive and safer pedestrian environment. Improvements will include new paving and road surfacing, improved and attractive lighting, improved road crossings and bus waiting facilities, better facilities for cyclists and improved amenity spaces including Beckenham Green.
Extensive planning and consultation has been carried out since the scheme was proposed in 2012. The cooperation and input of the ‘Town Centre Team’ and its members including the Beckenham Business Association, The Beckenham Society and the Copers Cope Resident Association is gratefully acknowledged, with their input key in shaping the nature of the scheme.
Sign up for regular newsletter updates
Businesses and interested residents who want to follow the progress of the work over the next 18 months can sign up for the regular updates that will be sent. Visit http://www.bromley.gov.uk/beckenhamimprovements to do this where the latest detailed traffic diversions are listed including information about bus routes and a link to TfL’s website http://www.tfl.gov.uk/BusChanges.
.
Thank you for your understanding and support
Every effort is being made to minimise disruption and your understanding and support is appreciated in advance if there are unforeseen issues which need to be resolved. If further specific information is needed, please contact Conway’s Helen McConnell who can be contacted, for help and advice. Helen, the Liaison Officer is the scheme contact for businesses and residents. Helen can be contacted on Mobile Tel 07917 518 529
or email Beckenham@fmconway.co.uk if needed.
Follow us on Twitter @FMConwayltd or find out more about our unique self-delivery model through our co
Dear Business Representative or Resident,
Friday 9th June 2017
Beckenham Improvements work update
Work for weeks commencing the 12th June 2017.
· Excavation work for new kerbs will be commenced between Pierluigis restaurant and approximately the Beckenham Pharmacy. Parking will be suspended in this area.
The entrance to Rokewood Apartments will be closed to vehicles for a minimum time from 8:00am on Tuesday 20th June through to Thursday 22nd at 16:30pm. Residents and users of this car park are being notified. Alternative parking will be arranged during this time for authorised users. If you do not need to use your car during these dates it can remain in situ.
If you are affected by this and have not contacted FM Conway’s liaison officer Helen McConnell please could you email Beckenham@fmconway.co.uk detailing your address, car make, model and registration number. Alternatively you can call Helen on 07917 518 529
· The construction of the new planters on Beckenham Green will continue. The structures have been designed in consultation with the Councils arboriculturalist. Each root will be boxed in a pipe/chamber to protect it with leverage for growth.
· Transport for London will continue to carry out modification works to the traffic signals on the corner of Albemarle Road and the High Street.
Previous completed works
· Kerbing and paving on Bromley Road has been completed.
· Foundations for the planters on Beckenham Green have been commenced.
· Preparation works for new kerb alignment between 106 High Street and 62 High Street Thorntons Corner have been carried out.About the scheme
The scheme is designed to make the town more attractive to visitors and shoppers by day and night. A major objective is to support existing businesses and encourage new businesses to invest in the town centre. The High Street investment improvements will
create a more attractive and safer pedestrian environment. Improvements will include new paving and road surfacing, improved and attractive lighting, improved road crossings and bus waiting facilities, better facilities for cyclists and improved amenity spaces including Beckenham Green.
Extensive planning and consultation has been carried out since the scheme was proposed in 2012. The cooperation and input of the ‘Town Centre Team’ and its members including the Beckenham Business Association, The Beckenham Society and the Copers Cope Resident Association is gratefully acknowledged, with their input key in shaping the nature of the scheme.
Businesses and interested residents who want to follow the progress of the work over the next 18 months can sign up for the regular updates that will be sent.
.
Visit www.bromley.gov.uk/beckenhamimprovements to do this where the latest detailed traffic diversions are listed including information about bus routes and a link to TfL’s website www.tfl.gov.uk/BusChanges.
Thank you for your understanding and support
Every effort is being made to minimise disruption and your understanding and support is appreciated in advance if there are unforeseen issues which need to be resolved. If further specific information is needed, please contact Conway’s Helen McConnell who can be contacted, for help and advice. Helen, the Liaison Officer is the scheme contact for businesses and residents. Helen can be contacted on Mobile Tel 07917 518 529 or email Beckenham@fmconway.co.uk if needed.
Helen McConnell
Business Liaison Officer
FM CONWAY
Mobile 07917 518529
Follow us on Twitter @FMConwayltd
What?
Founded in October 2016, the Beckenham Forum is an online meeting place for the residents of Beckenham to share their knowledge and experiences of life in the area.
Who?
The Beckenham Forum is not a faceless franchise based in California, we are a local couple living in Village Way, Beckenham.
Why?
We created the forum because we believe that being part of a community makes living somewhere much more enjoyable. An online community is something you can use where and when you want to.
New Features and how to upload images to your posts.
Video services by our sister company Beckenham Productions